Focus in

Engineer

Phases

Advice

Engineers should take care when copying and pasting details from one project to another. Some details cause a lot of installation problems (resulting in increased cost/time).

Advice

Sizing comments: 20’ x 30’ grid spacing is problematic for installation due to panel sizes, double or triple storey walls or columns present unique installation problems, even in terms of coordinating bracing with floor levels. It is difficult to keep 30’+ walls plumb.Dedicated to helping developers, engineers, installers, manufacturers, and more, we help you discover the growing power of mass timber’s functionality, cost-efficiency, and sustainability.

Image c/o: StructureCraft

Advice

Understand all aspects of the process, starting with the design, detailed design, and the fabrication model, all the way through to installation. If there are any parts not fully understood or covered by you or your team, hire expertise to fill the gaps as early as possible.

Advice

Design Bid Build can often be too formal if everything runs through the contractor. It is simpler if, for example, the engineer can talk directly to the architect. A carefully worded RFI can be helpful.

Advice

For private projects, and early fixed pricing, use a modified design build or design assist (= design build but with a formal tender). Spec loads, performance, preliminary sizing and connections, etc. and go out for a price at that point.