Steel connectors should be the responsibility of the same party that owns the timber manufacturing scope. They should be modelled at the same time, resulting in the purchase of the correct parts.
Other Articlees
Related Reading
Advice
Example of a mainly successful project: Brock Commons — involved a high degree of collaboration: Integrated Design Process — design offered 3-4 options for every connection, which every stakeholder vetted — invested in building a mock-up, where many problems were solved in advance of construction — the design worked with standard panel sizes
Advice
Tolerances are different for each different trade. Mitigate potential problems with communication in the procurement phase.