Focus in

Construction

Roles

Advice

Costs can easily inflate for MEP (mechanical, electrical, plumbing). Contractors go to suppliers for pricing, suppliers add contingency costs, contractors add their own contingency, and the cost can inflate enough to kill the project.

Advice

Mass panel installation advice: — Full scale mockup is a benefit, allows best practices to be developed and solutions identified prior to construction. — “Install prefab guardrail systems between columns on the perimeter and pre-determine tie-off points for worker safety” — Manufacturers need to clearly identify and locate balanced panel lifting points. — Pre plan and optimize truck load stacks, delivery schedules and erection sequencing