Designed for both industry experts and newcomers across the supply chain, Mass Timber Planning is a platform and knowledge base that addresses mass timber’s implementation, delivery methods, and best practices.

Dedicated to helping developers, engineers, installers, manufacturers, and more, we help you discover the growing power of mass timber’s functionality, cost-efficiency, and sustainability.

Sharing Value

Hot Posts

We help shape an unparalleled learning environment that is informed by industry experts. Browse through our key posts to stay up-to-date on trends and broaden your knowledge base.

Image c/o: StructureCraft

Advice

Understand all aspects of the process, starting with the design, detailed design, and the fabrication model, all the way through to installation. If there are any parts not fully understood or covered by you or your team, hire expertise to fill the gaps as early as possible.

Advice

The timing of contractor engagement impacts the ability to get construction input on structural assembly sequence & detailing.

Advice

A bracing plan is important, and has a large effect on installation. Establish a bracing plan early and integrate it into the connection details. A good bracing plan allows the connections to assist with temporary stability and requires over-designing, but saves time, money, headaches, and patching.

Branching Out

All Posts

Looking for inspiration? Filter your search by the various Roles and Phases to see what industry experts have to say about Mass Timber.

Roles

Phases

Advice

Using a single CAD model works well, with collaborative input from all trades (rather than attempting to combine multiple models from the different trades). This opens up more opportunities for accurate pre-drilling.

Advice

A bracing plan is important, and has a large effect on installation. Establish a bracing plan early and integrate it into the connection details. A good bracing plan allows the connections to assist with temporary stability and requires over-designing, but saves time, money, headaches, and patching.

Advice

Plan sequencing for fast placements. Connections often don’t work as a result of placement sequence. For example, more expensive connections can be used (eg Megant-style) where the assembly order doesn’t matter, but if cost is saved on the connections, time is wasted on site with necessary last minute adjustments.

Advice

Engineers should take care when copying and pasting details from one project to another. Some details cause a lot of installation problems (resulting in increased cost/time).

Advice

Sizing comments: 20’ x 30’ grid spacing is problematic for installation due to panel sizes, double or triple storey walls or columns present unique installation problems, even in terms of coordinating bracing with floor levels. It is difficult to keep 30’+ walls plumb.Dedicated to helping developers, engineers, installers, manufacturers, and more, we help you discover the growing power of mass timber’s functionality, cost-efficiency, and sustainability.

Image c/o: StructureCraft

Advice

Understand all aspects of the process, starting with the design, detailed design, and the fabrication model, all the way through to installation. If there are any parts not fully understood or covered by you or your team, hire expertise to fill the gaps as early as possible.