Prefabrication was good for full design of MEP, as it allowed for accurate off-site cutting of ducts, pipes, other systems and partial off-site assembly of the mechanical room.
Other Articlees
Related Reading
Advice
Example of a mainly successful project: Brock Commons — involved a high degree of collaboration: Integrated Design Process — design offered 3-4 options for every connection, which every stakeholder vetted — invested in building a mock-up, where many problems were solved in advance of construction — the design worked with standard panel sizes
Advice
Tolerances are different for each different trade. Mitigate potential problems with communication in the procurement phase.