Peel and stick membranes on CLT panels is inadequate for inclement weather. The best solution is to erect rapidly and install building envelope ASAP.
Other Articlees
Related Reading
Advice
Example of a mainly successful project: Brock Commons — involved a high degree of collaboration: Integrated Design Process — design offered 3-4 options for every connection, which every stakeholder vetted — invested in building a mock-up, where many problems were solved in advance of construction — the design worked with standard panel sizes
Advice
Tolerances are different for each different trade. Mitigate potential problems with communication in the procurement phase.