Elimination of beams and column grid optimization reduced the number of pieces and crane lifts required.
Focus in
Advice
Elimination of beams and column grid optimization reduced the number of pieces and crane lifts required.
Advice
Using a flat slab concept for CLT panels reduced the volume of wood used.
Advice
Limit areas of innovation to the structural system.
Advice
Engage the “authority having jurisdiction” early to ensure timely approval.
Advice
Scrutinize each design proposition to look for pitfalls.
Advice
“Constant and frequent communication” encouraged all to take ownership of project and actively contribute.
Advice
Tolerance discrepancies are +/- 24 mm for concrete and +/- 3 mm for wood).
Advice
Minimize error possibility by allowing all team members (design, fabricators, manufacturers and all trades) adequate time to have access to a common design platform.
Advice
Use BIM and an integrated project delivery (IPD) system from the start of the project.
Advice
Using a single CAD model works well, with collaborative input from all trades (rather than attempting to combine multiple models from the different trades). This opens up more opportunities for accurate pre-drilling.
Advice
Sizing comments: 20’ x 30’ grid spacing is problematic for installation due to panel sizes, double or triple storey walls or columns present unique installation problems, even in terms of coordinating bracing with floor levels. It is difficult to keep 30’+ walls plumb.Dedicated to helping developers, engineers, installers, manufacturers, and more, we help you discover the growing power of mass timber’s functionality, cost-efficiency, and sustainability.
Advice
Early discussions should involve all parties: installer, manufacturer, architect, engineer, owner/developer. Design with the people who will build the project, from fabrication to installation.
Advice
Unless you control or understand the flow of material and information from “forest to frame”, you will have blind spots; you will be derailed by cost, schedule, quality, or all three. For…
Advice
For public projects, consider getting expert timber engineers to look at connections (Design Assist delivery model).