Focus in

Planning

Roles

Advice

Specs should request written description of moisture protection protocol (submitted prior to CLT delivery), describing protection implementation plan for each stage: — delivery — storage — installation (roof & floor panels) — after installation (walls) — ongoing moisture protection measures until exterior envelope is watertight — remedial measures for panels damaged and/or stained during installation

Advice

The project must have comprehensive architectural and structural specs. Assume the proponents have no experience, which will ensure that everything is spelled out.

Advice

Spec a target tolerance. Contractually this is difficult to hold to, but provides a method to explain the importance of the allowable tolerance.